HVAC
IX2’s multiple, HVAC Liebert units are tied into
the building’s fully redundant central plant
system. The building’s system is equipped with
three (3) 1000 ton and two (2) 500 ton
centrifugal chillers with four (4) 1500 ton
cooling tower cells. Only one of the building’s
1,000 ton chillers are required to cool the
entire building. The building’s pumps and
chiller controls are tied into the emergency
generator and UPS system, which allows for
cooling to automatically continue in the event
of a power outage. |